Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74488 REL 4: 1992-061-02 EXP ALBENI FALLS WILDLIFE MITIGATION - KALISPEL
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Kalispel Tribe
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
74488 REL 4
Contract Title:
1992-061-02 EXP ALBENI FALLS WILDLIFE MITIGATION - KALISPEL
Contract Continuation:
Previous: Next:
75395: 1992-061-02 EXP ALBENI FALLS WILDLIFE MITIGATION
  • 74488 REL 13: 1992-061-02 EXP ALBENI FALLS WILDLIFE MITIGATION - KALISPEL
Contract Status:
Closed
Contract Description:
This project is for partial mitigation of wildlife habitat losses associated with the construction and inundation by Albeni Falls Dam as consistent with the NPCC Program and Power Act. Along with active restoration and enhancement activities, this contract will provide for data collection to provide scientific support for the continuation of these types of enhancement activities on additional properties as they become part of this project. This contract will also cover the operation and maintenance of existing habitat value and previously installed structures and improvements.

Traditionally, the Kalispel Tribe relied on the Pend Oreille River Basin and its abundant aquatic and terrestrial resources for subsistence. The productivity of the area has changed dramatically over the past sixty years due to the construction and inundation by Albeni falls Dam. Until the Pacific Northwest Power Planning and Conservation Act (Power Act) of 1980 (Public law 96-501) directed that measures be implemented to protect, mitigate, and enhance fish and wildlife to the extent affected by development and operation of hydropower projects on the Columbia River System and that the Bonneville power Administration provide funding to offset identified impacts. The construction of Albeni Falls dam resulted in the loss of over 20,000 Habitat Units in wetland and riparian habitat types. These losses occurred exclusively within the Kalispel adjudicated lands. Through the acquisition of property rights (fee title to management agreements), property protection, and habitat enhancement, the Kalispel Tribe is continuing to mitigate for these losses. This ongoing project (#1992-061-02) provides for the protection, enhancement, restoration, and operation and maintenance (O&M) of acquired lands to offset the negative impacts to wildlife species and habitats affected by the construction and operation of Albeni Falls Dam. Management activities include hydraulic restoration, wetland enhancement, shoreline protection, and vegetation restoration and enhancement. Along with active management activities, this contract will monitor past accomplishments to provide scientific support for the continuation of these types of enhancement/restoration activities as applied to additional properties as they become part of this project. This contract will also cover the O&M of existing habitat value and previously installed structures.
Account Type(s):
Expense
Contract Start Date:
03/01/2018
Contract End Date:
02/28/2019
Current Contract Value:
$1,032,857
Expenditures:
$1,032,857

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Matthew Berger Kalispel Tribe Yes Contract Manager mberger@knrd.org (509) 447-7244
Ray Entz Kalispel Tribe Yes Supervisor rentz@knrd.org (509) 445-1147
Bart George Kalispel Tribe Yes Technical Contact bgeorge@kalispeltribe.com (509) 671-6149
Kendra Maroney Kalispel Tribe No Interested Party kmaroney@kalispeltribe.com (509) 671-2376
Jolene Seymour Kalispel Tribe No Administrative Contact jseymour@kalispeltribe.com (509) 445-1147
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Jennifer Snyder Bonneville Power Administration Yes Env. Compliance Lead jasnyder@bpa.gov (503) 230-4187
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Completion of Required Project Reporting to BPA B: 119. Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies 02/28/2019 02/26/2019
Completed documentation of environmental compliance to BPA C: 165. Complete Permit Applications and Provide Documentation to Obtain Compliance. 02/28/2019 02/26/2019
Coordination complete D: 191. Internal Coordination 02/28/2019 02/26/2019
Completed Acquisition and Easement Agreements E: 172. Pre-Acquisition work 02/28/2019 02/26/2019
Completed FY18 Annual Report to BPA F: 132. Annual Report for 2018 Contract Cycle 02/28/2019 02/26/2019
Maintain Existing fence G: 186. Fence Maintenance Idaho 02/28/2019 02/26/2019
Create and enhance Wetland Ponds and plug drainage ditches. H: 181. Create and enhance Wetland Ponds on Washington Management Area 02/28/2019 02/26/2019
Wetland Ponds and shorelines seeded and mulched I: 47. Seed Newly Created Wetland Pond Shorelines 02/28/2019 02/26/2019
Properties Secured From Trespass J: 26. Secure Properties and Provide Enforcement Management. 02/28/2019 02/26/2019
Maintain access to water control structures. K: 38. Maintain access to water control structures. 02/28/2019 02/26/2019
Water Control Structures Maintained and Functioning L: 186. Maintain Existing Water Control Structures on Wetland Enhancement Sites. 02/28/2019 02/26/2019
Buildings and nursery maintained M: 186. Maintain buildings 02/28/2019 02/26/2019
Vegetation Removal Idaho lands N: 199. Removal Vegetation Idaho 02/28/2019 02/26/2019
Maintain planted vegetation in Washington. O: 198. Maintain planted vegetation in Washington 02/28/2019 02/26/2019
Provide parking areas and kiosks for visitors P: 188. Provide parking and kiosks for visitors 02/28/2019 02/26/2019
Maintenance of Vegetation on Idaho properties Q: 198. Maintain planted vegetation in Idaho 02/28/2019 02/26/2019
Fence Maintenance Washington R: 186. Fence Maintenance Washington 02/28/2019 02/26/2019
Planted Riparian Areas on Enhancement Sites S: 47. Plant Native Trees and Shrubs-WA mgt areas 10/31/2018 10/31/2018
Remove Vegetation Washington T: 199. Remove Vegetation WA Mitigation Properties 02/28/2019 02/26/2019
Field Nursery maintenance U: 198. Maintain field Nursery for plant materials 02/28/2019 02/26/2019
Land Management Plans V: 193. Complete Management Plans for new acquesitions 02/28/2019 02/26/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 199 Remove Vegetation
  • 3 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 26 Investigate Trespass
  • 4 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2018
B 119 Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies 03/01/2018
C 165 Complete Permit Applications and Provide Documentation to Obtain Compliance. 03/01/2018
D 191 Internal Coordination 03/01/2018
E 172 Pre-Acquisition work 03/01/2018
F 132 Annual Report for 2018 Contract Cycle 03/01/2018
G 186 Fence Maintenance Idaho 03/01/2018
H 181 Create and enhance Wetland Ponds on Washington Management Area 03/01/2018
I 47 Seed Newly Created Wetland Pond Shorelines 03/01/2018
J 26 Secure Properties and Provide Enforcement Management. 03/01/2018
K 38 Maintain access to water control structures. 03/01/2018
L 186 Maintain Existing Water Control Structures on Wetland Enhancement Sites. 03/01/2018
M 186 Maintain buildings 03/01/2018
N 199 Removal Vegetation Idaho 03/01/2018
O 198 Maintain planted vegetation in Washington 03/01/2018
P 188 Provide parking and kiosks for visitors 03/01/2018
Q 198 Maintain planted vegetation in Idaho 03/01/2018
R 186 Fence Maintenance Washington 03/01/2018
S 47 Plant Native Trees and Shrubs-WA mgt areas 03/01/2018
T 199 Remove Vegetation WA Mitigation Properties 03/01/2018
U 198 Maintain field Nursery for plant materials 03/01/2018
V 193 Complete Management Plans for new acquesitions